Jammu & Kashmir State Power Development Corporation is planning the Sawalkote Hydroelectric Power project.

30 Jan

Company : Jammu & Kashmir State Power Development Corporation

Location : River Chenab

Status : Planning Stage

[signinlocker]Jammu & Kashmir State Power Development Corporation is planning the 1,856 MW Sawalkote Hydroelectric Power project on River Chenab, dist. Ramban, Jammu and Kashmir. The estimated cost of the project is Rs. 4.3 billion. The project is expected to be executed in 2 phases. Tender finalization is in progress for appointment of consultant. Tender is yet to be floated for contractors. Land has been identified and acquisition is in progress. The project is waiting for environmental clearance. The entire project is expected to be commissioned in 8 years from zero date.[/signinlocker]