IL&FS Engineering Bags Rs 162.58 Cr Order From GAIL
Company | GAIL Limited |
Location | Bihar |
Source | BS, Oct 12,’16 |
GAIL has issued an order to IL&FS Engineering and Construction Company for a pipeline in Bihar. The order involves laying and construction of pipeline along with associated facilities of section II pipeline from Chainage 159.70 km to Receiving Terminal Cum Future IP Station-4 at Dobhi (Chainage 345.08 km.) for Phulpur-Haldia Pipeline Project (Phase 1B) in Bihar. The total length of the pipeline is 185.38 km and the total value of the contract is Rs 162.58 crore. The project is to be mechanically completed in 15 months from date of FOA and with additional 3 months for drying, commissioning and GAS-IN. |